Project Timeline

The 3 facilities will be implemented over a 5 year period from 2018-2023. You can find key milestones for the CCS RBF and SSP RBF facilities below.

CCS RBF = Clean Cooking Solutions Challenge Results-Based Financing Facility

SSP RBF = Solar Service Providers Results-Based Financing Facility

  • All

    Facilities launch

     11th June 2019

  • CCS RBF

    Sharing information packages and booking for pre-application workshops

     12th -21st June 2019

  • CCS RBF

    Pre-application workshops

     24th -28th June 2019

  • SSP RBF

    Pre-bidding orientation

     25th - 27th June 2019

  • CCS RBF SSP RBF

    Open call for proposals

     1st July 2019

  • SSP RBF CCS RBF

    Deadline for submissions

     30th August 2019

  • CCS RBF SSP RBF

    Feedback to applicants

     1 week

  • SSP RBF CCS RBF

    Evaluation of proposals and due diligence

     3 weeks

  • CCS RBF SSP RBF

    Awarding and contracting

     3 weeks

  • CCS RBF SSP RBF

    Commencement of implementation

     2 weeks after contracting